CALA Foods Market Story Print E-mail
Sunday, 05 July 2009
Article Index
CALA Foods Market Story
Page 2
Page 3
Page 4
Page 5

Chronology of the 690 Stanyan (CALA) Proposed Project

13 June 2005- first filing for a new project at 690 Stanyan of 57 units and 100 parking spaces received by Planning Department from Brennan . Filing this soon exempts project from new inclusionary requirement of 15% having it meet the old 12% requirement.

15 Feb 2006 - First Public Notice of demolition of CALA site mailed to occupants listing only one lot on Stanyan when Brennan plans call for a project on two lots.

27 Feb. 2006 - 15 Feb notice withdrawn and new notice for two lots on Page and Stanyan issued. Additional 30 day review period because of inaccurate first notice.

20 March 2006- Planning Department Notice that project application is on "Hold" pending information required for PUD and application for EE which of this date had not been submitted by Brennan's. Project description enlarged from 57 to 62 units and 184 parking spaces from 100. Size of commercial space for project doubled.

13 Apr. 2006- HANC monthly meeting devoted to a discussion of ‘Preferences" for CALA site. Some 21 are listed and sent developer (who was present at meeting) and Plan Depart. List was published in May, 2006 HANC Voice. The April HANC meeting was the first public meeting held on the project in the neighborhood.

May 2006- CALA is closed

13 July 2006- Mark Brennan attends HANC monthly meeting to respond to "Preferences" of HANC's Apr meeting. Says there will be no interim uses on site until project is approved

25 October 2006 - Official Notice of Project Receiving Environmental Review for 690 Stanyan, some 7 months after request for application for environmental evaluation.

14 June 2007- HANC membership meeting discusses approval and EIR process for CALA site with Planning Department lead project planner Jonas Ionin. Developer present.

7 July 2007-Notice of Preparation of EIR ("Initial Study") issues for 690 Stanyan

3 Aug. 2007- HANC submits "Comments on Scoping of EIR 206.046E 690 Stanyan".

13 September 2007- HANC Board votes to oppose project.

19 Jan. 2008- Draft EIR for 690 Stanyan published

2 Feb. 2008- HANC sponsored neighbors meeting on 690 Stanyan where it is learned that the immediate neighbors have never been approached or directly notified by the Brennan's of their pending project.

8 Feb. 2008 - Plan Com Approves Parking Lot for 690 Stanyan

28 Feb. 2008 - Public Hearing on Draft EIR, HANC, Sierra Club and some 20 or so residents submit written comments pointing out incompleteness of traffic impacts studies.

1 October 2008- Comments and Responses to EIR document published. It took the developers 8 months to respond to comments made at 28 Feb hearing.

18 October 2008 - HANC sponsored neighbors meeting on 690 Stanyan

23 October 2008 - Project approved and final EIR certified.

28 May 2009- Mark Brennan tells SF Business Times project is "scrapped" because of financing some 7 months after getting approval.


 